O’Neil Road and Shoulder Reconstruction

Shire of Northam is located 96 kms away from Perth.

The scope of works includes bit not limited to reconstruction of shoulders of O’Neil road from SLK 0.00 to 1.1 both sides and reconstruction of existing road section within the same SLK. The scope includes reinstatement of V-drains along the reconstructed shoulder and repair of seal edge.

  • Site clearing
  • Disposal of surplus and unusable material
  • Shoulder reconstruction that ripped of and allow 150mm thick imported 2% cement stabilised gravel and as per Main Roads Specification passed
  • Reinstate V-Drains
  • Road Reconstruction
  • Seal edge repair